On The Edge WynnWood Informer Volume 1 Issue 7 |
|
Time sure flies! It seems only yesterday that I was writing last months update. Highlights for June include: · Fortis power cables upgraded · Tray sorter and automatic end stacker have been installed · The first stage of the tilt hoist has been rebuilt and second stage has arrived from Mill Tech. Installation of the two-stage system has started. · Carpenters continue to work on the interior of the building, finishing shops, offices and storage rooms · Foundation for the 50’ cyclone has been poured. Delivery of cyclone and other components of the air system from AirTek are expected next week. Start-up representatives from Iron Code, Autolog, Mill Tech, and Ackhurst will be onsite in July. We all look forward to the sound of equipment running! Colin. |


|