The mill is now powered up but, we have fallen a little behind in our startup schedule. The initial startup phase went well as we have tested the moulder and trim line. Other progress for July includes: - Completion of two-stage tilt hoist. The tilt hoist infeed transfer has been started but still requires a few days to complete - Construction of the chipper room is complete - Installation of the vibrating conveyor for trim blocks is complete - Installation of the bins, two cyclones, blower is complete We will be testing more equipment in the coming weeks with plans to have the first production though the moulder the week of August 25th, 2008. A special note to all employees and contractors working on the project – Great work so far… the celebration is just around the corner! Colin. |


|