The Progress is Amazing |
2 |
|
|
|
|
|
|
|
|
|

|
Despite the bitter cold and unusually high snowfall during the last two weeks, we continue to make solid progress on the new mill. Many thanks to our dedicated workforce and contractors from Corbilt/AJ Equipment Installations and Ninco Construction Ltd for their hard work and perseverance. Highlights for the period include: · Completion of site preparation · 80% completion of footings and 60% completion of pedestals for building columns · Arrival of the first shipments of grade and trim line equipment from Mill Tech Industries of Salmon Arm BC. Arrangements have been made to visit the LMC LeaderMac manufacturing facility in Taiwan for final inspection and loading of the Super Thundermac moulder. Delivery to mill site is planned for mid March. |
|